Tulsa Ice Arena Rises From Vacant Department Store
HomeHome > News > Tulsa Ice Arena Rises From Vacant Department Store

Tulsa Ice Arena Rises From Vacant Department Store

Aug 04, 2023

Trusses are transforming a former Macy’s department store in Tulsa into an ice rink.Image courtesy of Perkins&Will

A team led by architect Perkins&Will and Thompson Construction is creatively using inverted bowstring trusses to transform a 1994-built Macy’s department store into the slick WeStreet Ice Center.

As the training headquarters for the ECHL Tulsa Oilers, the 180,000-sq-ft arena will include two rinks on the ground floor, one with spectator seating for 1,000 and the second, a practice rink, with fewer seats. There will also be a concession area; locker rooms; party spaces for corporate events and birthdays; lounges; medical treatment areas; coach offices; and an Oklahoma State University club hockey locker room. The second floor adds an enclosed restaurant and administrative offices, both with views of the ice.

Led by Andy Scurto, owner of the Tulsa Oilers and the WeStreet Ice Center, the design/construction team includes structural engineer Martin/Martin Inc.; ME Engineers, performing mechanical work; Thompson, the construction manager at-risk; and the owner’s representative, International Coliseum Co., for furniture, fixtures and equipment. The $25-million sports facility, about 15 miles from downtown in a challenged mall, is a partnership with WeStreet Credit Union. Completion is expected during late fall.

The public will use the rink when the Tulsa Oilers hockey team is not playing or practicing. Image courtesy of Perkins&Will

When Scurto first considered the space conversion in the summer of 2022, the team members realized the project would require extensive engineering to convert a traditional bar-and-joist-structured department store, built in 1994, to a dual-rink ice facility in which 40% of the interior columns would have to be removed for the long-span trusses above the rinks. In addition, to provide the support spaces, such as the restaurant, 40% of the second story would also have to be demoed.

“Our biggest challenge was, ‘Can we do it in a cost-effective way that makes sense,’” says Don Dethlefs, sports, recreation and entertainment global practice leader and principal of the Denver studio for Perkins&Will. He and Emily Cannon, designer III, are leading the company team. Dethlefs adds, “What’s more, the owner wanted the building ready for the fall hockey schedule.”

The structure will also include team offices and public spaces.Image courtesy of Perkins&Will

With Martin/Martin, the team decided that the project could be engineered within a budget that would be acceptable to Scurto and his group. Fortunately, the roof was in good condition, which ensured dried-in space for the construction.

But a conventional structure had to become an unconventional one. “We had to devise a way to free span the opening required for the ice rinks without columns and without impacting the existing roof structure or hindering the fans’ sight lines,” Cannon says.

Martin/Martin suggested that an inverted bowstring truss would meet project requirements geometrically, architecturally and structurally to support the existing roof. “Structural challenges to reframe a conventional bar joist and joist-girder roof to create a long-span roof system and column-free space is unique to the WeStreet Ice Center,” says Scott Wert, senior project engineer at Martin/Martin.

He explains: A traditional bowstring truss is oriented with the curved ‘bow’ at the top chord of the truss and a flat bottom chord. But the existing roof required an inverted configuration to flush the top chord at the roof and limit overall truss depth.

The original column spacing was 32–40 ft, and the new truss systems span 112 ft (six per rink) while limiting truss depth to less than 9 ft to maintain sight lines. “The shape itself allows for the top chord to be flat and tight to the existing roof structure, while the bow shape of the bottom chord allows for a shallow profile at the ends where second level view lines are needed and a deep profile at midspan where depth is needed structurally,” he adds.

He says that maximum flexure occurs at midspan, which coincides with maximum truss depth, and is theoretically zero at the ends, coinciding with zero truss depth. “Therefore, the bowstring truss closely follows the flexural demands on the truss and allows for efficient use of materials by using depth where we need it and having a shallow profile where we don’t.”

The addition of a long-span truss in an existing building concentrates load to a smaller number of columns and foundation elements, dictating the removal of some columns and strengthening some foundations. As a result, Thompson removed 18 columns per rink—36 total. In addition, the crew demoed 16 footings at the ends of the new trusses and replaced these with larger ones to carry the new concentrated load.

During demolition and construction, each of the columns that would remain had to be jacked and shored; this required significant coordination and additional engineering by the contractor to maintain structural stability and ensure a safe working space. “These operations become even more complicated at the columns in the middle of the truss spans where specific jack heights and column elevation monitoring were required,” Wert says. “The contractor monitored each column closely during these operations to ensure that, as much as possible, the roof deflected back to a neutral position relative to the existing structure and within a specified elevation tolerance.”

Construction on the $25-million project started in the summer of 2022.Image courtesy of Perkins&Will

Centered on the roof, the mechanical penthouse complicated the truss design because of the increased weight. The team was challenged by the asymmetrical concentration of that load at the ends of each truss and the need to limit disturbance and distress to the rooftop structure from jacking and shoring operations as well as truss deflections under service loads, Wert says.

Construction of the rink stadia and the tiers of elevated seating rows also required creative design. Rather than building conventional precast or prefabricated stadia, which would be difficult to install and maneuver within the building, the team designed them with steel rakers and stadia beams on a slab-on-metal deck.

Throughout the process, Thompson used technology and other innovations to maintain communication. For instance, the use of Procure allowed for the consolidation and tracking of drawings, specs, RFIs, submittals, daily reports, photos and construction issues. And, to maximize the lighting control without cluttering the large open ceilings throughout the project, a wireless control system allows the sensors and control points to connect without spending the time or money to wire them together. “This form of lighting control is new to the industry, but for this project [it was] a very fitting application,” Dethlefs says.

Hockey fans can catch a game and grab a brew at the rink’s restaurant. Image courtesy of Perkins&Will

During the first site visit, the team found a 750-ton three-chiller water-cooled central plant and a 120,000-cfm built-up air-handling unit in the rooftop penthouse, which had cooled the department store.

“Though the chiller pumps were in great condition, it was clear that the cooler towers needed repairs and upgrades. We were hopeful it would be a quick upgrade with a little bit of maintenance and services,” says Jeff Ewens, representative for ME Engineers. The design/construction team commissioned a mechanical contractor to do a startup test on the plant to ensure that it was functional.

But two of the three chillers, as well as the cooling towers, required costly repairs to incorporate the existing plant into the new project. The team connected with manufacturers, and Tulsa-based AAON collaborated with Thompson and ME Engineers to develop an ice rink unit, which will be placed just outside the penthouse and provide appropriate cold, dry air conditions needed for ice hockey operation.

Meanwhile, other chillers being installed by the loading dock are dedicated to creating and maintaining the ice sheets. This equipment is designed and provided by CIMCO. Interior air-conditioning is being variously supplied by package rooftop units (RTUs); VRF heat pumps with indoor units located in or above the spaces they serve; and a specialized rooftop unit with ducts to the ice rinks.

Overall scheduling has been an issue as well. The owner allotted the team 18 months from design kick-off to the opening. Thompson received a preliminary demolition permit in August 2022, but final construction documents weren’t issued until December; this led to much of the design overlapping with construction, Dethlefs says. “But this created the opportunity for our team to coordinate internally as well as with Thompson to identify critical path items that would need to be fast-tracked due to industry volatility,” he says.

The revitalization of the space should bolster the local economy and unite the community, Scurto says. “The new ice center will bring thousands of people to the mall and should bring back the use of all the shops and give people a reason to return and enjoy the area for shopping, services and entertainment.”

Trussworthy“Our biggest challenge was ‘Can we do it in a cost-effective way that makes sense.’” A Score of ChallengesChiller on the Rooftop